E-DISTRIBUTIE MUNTENIA INVESTED 14.5 MILLION LEI FOR THE MODERNISATION OF THE COTROCENI PRIMARY STATION
Thursday, December 14, 2017
E-Distributie Muntenia invested approx. 14.5 million lei (3.15 million euros) for the first stages of the modernization of the Cotroceni primary station in Bucharest, a 3-year project which began in 2016, with a total investment value of 18 million lei. The modernisation works completed so far at the 110/10 kV station included the commissioning of the new high voltage equipment, with hybrid modules. On the medium voltage side, ...